Soru
Edouard has found that he likes to organize his class assignments and projects by wook. Every Saturday he reviews what assignments he has due In the upcoming wook, and uses a schodule to assign start and stop times for each assignment he wants to complete. Which of the following does Edouard use to schodule his class assignments? A. Mastor B. Projoct C. Gantt D. PERT E. Daily
Çözüm
4.2279 Voting
Ferhat
Gelişmiş · 1 yıl öğretmeniUzman doğrulaması
Cevap
'C'
Açıklamak
## Step 1<br />The problem is asking us to identify the type of schedule Edouard uses to organize his class assignments. The options provided are Master, Project, Gantt, PERT, and Daily.<br /><br />## Step 2<br />We need to understand what each of these options represents. A Gantt chart is a type of bar chart that illustrates a project schedule. This chart lists the tasks to be performed, their duration, and the order in which they need to be done. This aligns with Edouard's method of scheduling his assignments.<br /><br />## Step 3<br />On the other hand, Master, Project, and Daily do not represent a specific type of schedule. They are more general terms and do not provide a structured way to schedule tasks.
Derecelendirmek için tıklayın: